All of the walls in phase one were:

  • Mudded where needed to fix holes and years of love to look not as patched worked or lumpy bumpy from adjustments to the walls in the past.
  • Painted with a coat of flat paint so the new texture will stick to the wall properly
  • Cabinets, windows, doors taped with plastic wrap
  • New electrical was ran for new location for TV installation.

Work done in phase two:

  • Removed base boards in the nursery hallway, puppet room, and about ½ of the lobby/bathroom hallway area
  • Removed bulletin boards, acrylic holders, old room signs, safety convex mirrors in bathrooms and a few other small things hanging on the walls
  • Removed staples, sheet rock screws in a few of the spaces
  • Refinishing 2 out 6 wood cabinets that we are keeping –they looks so good and like new!